Skip to main content
Court of Claims· 10/15/1965

Wunderlich Contracting Co. v. United States

Citations

  • 173 Ct. Cl. 180
  • 351 F.2d 956

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that the party seeking damages bears the burden to establish “the fundamental facts of liability, causation, and resultant injury”
  • holding that “[b]road generalities and inferences to the effect that defendants must have caused some delay and damages because the contract took . . . longer to complete than anticipated are not sufficient”
  • stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
  • stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
  • stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
  • stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Collins, Cowen, Davis, Durfee, Laramore

Read full opinion on CourtListener

Other cases named Wunderlich Contracting Co. v. United States

2 other CourtListener records share this case name.

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.