Court of Claims· 10/15/1965
Wunderlich Contracting Co. v. United States
Citations
- 173 Ct. Cl. 180
- 351 F.2d 956
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that the party seeking damages bears the burden to establish “the fundamental facts of liability, causation, and resultant injury”
- holding that “[b]road generalities and inferences to the effect that defendants must have caused some delay and damages because the contract took . . . longer to complete than anticipated are not sufficient”
- stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
- stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
- stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
- stating that a plaintiff asserting a claim for breach of an implied warranty of specifications has the “burden of establishing the fundamental facts of liability, causation, and resultant injury.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Collins, Cowen, Davis, Durfee, Laramore
Read full opinion on CourtListenerOther cases named Wunderlich Contracting Co. v. United States
2 other CourtListener records share this case name.
Sourced from CourtListener / Free Law Project (CC0).