P. L. Saddler v. United States

Citations

  • 287 F.2d 411
  • 152 Ct. Cl. 557
  • 1961 U.S. Ct. Cl. LEXIS 54

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • large increase in earthwork due to change in levee specifications held cardinal change falling outside scope of contract
  • near doubling of the amount of excavation required under contract to build a levee embankment was beyond the scope of the original contract and thus, Changes clause inapplicable
  • 100 percent increase in amount of earth moved constituted cardinal change
  • 10% overhead claimed as result of change order is reasonable

Source: CourtListener parenthetical corpus (CC0).