· 3/1/1961
P. L. Saddler v. United States
Citations
- 287 F.2d 411
- 152 Ct. Cl. 557
- 1961 U.S. Ct. Cl. LEXIS 54
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- large increase in earthwork due to change in levee specifications held cardinal change falling outside scope of contract
- near doubling of the amount of excavation required under contract to build a levee embankment was beyond the scope of the original contract and thus, Changes clause inapplicable
- 100 percent increase in amount of earth moved constituted cardinal change
- 10% overhead claimed as result of change order is reasonable
Source: CourtListener parenthetical corpus (CC0).
Judges: Durfee