· 12/13/1963

Laburnum Construction Corporation v. The United States

Citations

  • 325 F.2d 451
  • 163 Ct. Cl. 339
  • 1963 U.S. Ct. Cl. LEXIS 149

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • for depreciation purposes useful life of barge initiated when it became ready for service, not when put into use
  • measure of damages resulting from delay caused by defective speeifica- tions is the contractor’s actual costs during the period of delay
  • for depreciation purposes useful life of barge initiated when it became ready for service, not when put into use
  • “This exculpatory rule is not applicable to a situation in which unreasonable delays were the ... fault of the Government.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Jones, Whitaker, Laramore, Durfee, Davis

Read full opinion on CourtListener