Shell v. Schmidt

Citations

  • 330 P.2d 817
  • 164 Cal. App. 2d 350
  • 76 A.L.R. 2d 792
  • 1958 Cal. App. LEXIS 1617

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • holding that the breaching contractor has the burden “to affirmatively and convincingly prove that economic waste would result [and that] a substantial part of what has been done must be undone”
  • noting that when a contractor intentionally deviated from the plans and specifications, notwithstanding a claimed justification for the deviation, it was not entitled to the diminution in value damage measure, as good faith compliance is one of the elements of substantial performance
  • reviewing case law addressing when cost to repair, as opposed to diminution in value, is used as a measure of damage, and holding that burden was on defendant to establish that award of cost of repair was so economically wasteful as to warrant award of diminution in value

Source: CourtListener parenthetical corpus (CC0).

Judges: St. Clair

Read full opinion on CourtListener

Cited by

24 cases in this archive cite this case; the 20 most cited are listed.

Cites

11 cases in this archive are cited by this case.

Other cases with this name

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.