Skip to main content
· 1/4/1989

Key Constructors, Inc. v. H & M GAS CO.

Citations

  • 537 So. 2d 1318
  • 1989 Miss. LEXIS 8
  • 1989 WL 1314

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • noting that contractor was liable on the payment bond to a second-tier subcontractor even though the contractor had a valid defense against the first-tier subcontractor
  • Miss. Code Ann. § 31-5-57 provides for award of reasonable attorneys’ fees upon the furnishing of an evidentiary predicate therefor

Source: CourtListener parenthetical corpus (CC0).

Judges: Roy Noble Lee, C.J., and Robertson and Anderson

Read full opinion on CourtListener