Court of Claims· 7/15/1985

Fortec Constructors v. United States

Citations

  • 8 Cl. Ct. 490
  • 32 Cont. Cas. Fed. 73,702
  • 1985 U.S. Claims LEXIS 947

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • stating that “if the CPM is to be used to evaluate delay on the project, it must be kept current and must reflect delays as they occur”
  • the critical path method “breaks down the entire project into individual tasks and assigns a number of days anticipated to perform each task”

Source: CourtListener parenthetical corpus (CC0).

Judges: Yock

Read full opinion on CourtListener

Cited by

15 cases in this archive cite this case.

Cites

11 cases in this archive are cited by this case.

Other cases named Fortec Constructors v. United States

3 other CourtListener records share this case name.

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.