United States v. United Engineering & Contracting Co.
Citations
- 234 U.S. 236
- 34 S. Ct. 843
- 58 L. Ed. 1294
- 1914 U.S. LEXIS 1145
- 49 Ct. Cl. 689
Syllabus
<p>While reasonable contracts for liquidated damages for delay are not to be regarded as penalties and may be enforced between the parties, Sun Printing Ass’n v. Moore, 183 U. S. 642, one party must not prevent the other party from completing the work in time, and if such is the case, even if the subsequent delay is the fault of the latter, the original contract cannot be insisted upon and the liquidated damages are waived.</p> <p>Where the original contract for government work provided for liquidated damages for delay beyond a specified date but supplemental contracts contained no fixed rule for the time of completion, the Government is limited in its recovery to the actual damages sustained by reason of the delay for which the contractor was responsible.</p> <p>It is the English rule, as well as the rule in some of the States, that where both parties are responsible for delays beyond the fixed date, the obligation for liquidated damages is annulled; and, unless there was a provision substituting a new date, the recovery for subsequent delay is limited to the actual loss sustained.</p> <p>Where the Government has by its own fault prevented performance of the contract and thereby waived the stipulation as -to liquidated damages, it cannot insist upon it as a rule of damages beci use it may be impracticable tó prove actual damages.</p>
Judges: Day
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.