Supreme Court· 11/26/1917

Day v. United States

Citations

  • 245 U.S. 159
  • 38 S. Ct. 57
  • 62 L. Ed. 219
  • 1917 U.S. LEXIS 1753

Syllabus

<p>Modem tendencies to depart from the strict letter in discovering intent do not alter the principle that, within the scope of his undertaking, a party contracting assumes the risks of intervening obstacles.</p> <p>A contractor agreed with the United States to furnish, at specified rates, such labor and material in place as might be necessary to complete a canal and locks, already built in part, the total payment not to exceed a sum fixed in acts of Congress .authorizing the contract.. The Government had erected a bulkhead, deemed of sufficient height, to safeguard the work from river floods; the contract, however, did not guarantee protection, referring to freshets, and other natural causes, merely as grounds for time extension. The con- • tractor had been required to base his proposal upon personal investigation, and the specifications provided that he should be held responsible, without expense to the Government, for the preservation and good condition of the work already in place, and that to be added from time to time under the contract, until the contract should be terminated or the whole work turned over in a completed condition as required. To protect the work from an extraordinary flood which exceeded the bulkhead, the contractor necessarily expended work and materials in building new structures, for which he sought reimbursement in the Court of Claims. Held, that the contract was for the completion of the works and that the cost of protecting them from floods in the meantime was within the contractor’s undertaking.</p>

How courts have described this case

Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.

  • river levy construction contractor held liable for increased cost of levy due to delay caused by river flooding
  • river levy construction contractor held liable for increased cost of levy due to delay caused by river flooding
  • “[W]hen the scope of the undertaking is fixed, that is merely another way of saying that the contractor takes the risk of the obstacles to that extent.”

Source: CourtListener parenthetical corpus (CC0).

Judges: Holmes

Read full opinion on CourtListener

Cited by

54 cases in this archive cite this case; the 20 most cited are listed.

Cites

3 cases in this archive are cited by this case.

Other cases named Day v. United States

64 other CourtListener records share this case name; the 50 most cited are listed.

Sourced from CourtListener / Free Law Project (CC0).

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.