Wells Brothers Co. of NY v. United States
Citations
- 254 U.S. 83
- 41 S. Ct. 34
- 65 L. Ed. 148
- 1920 U.S. LEXIS 1242
Syllabus
<p>Where a contract for the construction of a public building, giving the United States a broad power to suspend operations where necessary in the opinion of its architects for the purpose or advantage of the work, permitted the United States to make changes of materials, and, besides providing against claims' for damages .on account of such changes, declared generally that no claim should be made or allowed to the contractor for any damages arising out of any delay caused by the United States, held, that a delay ordered to await an .appropriation by Congress for substituted materials and another in anticipation of the passage of a postal law because of which the plans were altered, would not support claims for damages under the contract. P. 85.</p> <p>54 Ct. Clms. 206, affirmed.</p>
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- clause allowed suspension but allowed extension of time only, no delay damages
Source: CourtListener parenthetical corpus (CC0).
Judges: Clarke
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.