· 3/13/1978
Builder's Concrete v. Faubel & Sons, Inc.
Citations
- 373 N.E.2d 863
- 58 Ill. App. 3d 100
- 15 Ill. Dec. 517
- 1978 Ill. App. LEXIS 2263
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- “Plaintiff stated unequivocally that it would not fulfill its part of the bargain and defendant was justified in taking plaintiff at its word.”
- A liquidated damages clause “must be a specified amount for a specific breach to be paid as an alternative to performance and not as a penalty for nonperformance.”
- A liquidated damages clause “must be a specified amount for a specific breach to be paid as an alternative to performance and not as a penalty for nonperformance.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Stengel
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.