St. Paul Dredging Co. v. State
Citations
- 259 Minn. 398
- 107 N.W.2d 717
- 1961 Minn. LEXIS 684
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding in accordance with federal cases that absent an exculpatory clause in the subcontract a contractor can recover for losses sustained by its subcontractor
- failure to procure the necessary cooperation of a third party to fulfill the state’s obligation to remove telephone poles did not excuse the state from performance, absent a specific contractual provision of excuse for that contingency
- “It is well settled that a promise which cannot be performed without the consent or cooperation of a third party is not excused because of the promisor’s inability to obtain such cooperation.”
Source: CourtListener parenthetical corpus (CC0).
Judges: Thomas Gallagher
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.