· 12/28/1978
Sornsin Construction Co. v. State
Citations
- 590 P.2d 125
- 180 Mont. 248
- 26 Cont. Cas. Fed. 83,215
- 1978 Mont. LEXIS 709
How courts have described this case
Verbatim parenthetical descriptions written by other courts when citing this decision. Ranked by citation-network relevance.
- holding that contractor entitled to additional compensation under changed conditions clause where depth of water greater than anticipated in plans interfered with placement and functioning of cofferdam
Source: CourtListener parenthetical corpus (CC0).
Judges: Harrison, Haswell, Daly, Shea, Sheehy
Read full opinion on CourtListenerSourced from CourtListener / Free Law Project (CC0).