EPA v. CITY OF PLUMMER WWTP
Final Order No Penalty
Case summary
On August 18, 2025, Region 10 issued an administrative order on consent to the City of Plummer for its wastewater treatment facility. From March 1, 2020, through February 28, 2025, the City of Plummer's wastewater treatment facility exceeded it's effluent limit 1,828 times. In addition to the effluent exceedance violations, the facility failed to submit required reports and notifications in a timely manner and did not maintain an adequate Operations & Maintenance (O&M) or Quality Assurance (QA) Plan. To return to compliance, the Respondent has agreed to submit a complete O& M Plan, a QA Plan and a Facility Plan. The Facility Plan is to ensure the facility comes into compliance with its effluent limits. Further, the facility is required to begin implementing the Facility Plan upon its completion. The estimated cost of implementing this injunctive relief is approximately $3,000,000.
Defendants (1)
- CITY OF PLUMMER WWTPNamed in complaintNamed in settlement
Facilities (1)
PLUMMER, CITY OF - PLUMMER WWTP
324 TOETLY ROAD (COEUR D'ALENE RESERVATION), PLUMMER, ID, 83851
Registry ID: 110013719075
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
CITY OF PLUMMER WWTPentered 2025-09-25
Primary law: CWA
Timeline (3 milestones)
- 2025-07-17Enforcement Action Data Entered
- 2025-09-25Complaint Filed/Proposed Order
- 2025-09-25Final Order Issued
Case metadata
- EPA activity ID
- 3604460024
- Case number
- 10-2025-0149
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations