Skip to main content
10-2025-0015Administrative - FormalClosedFY 2025· Region 10

EPA v. STICKS & STONES CONSTRUCTION LLC (ESA) (TSCA)

Final Order With Penalty

Case summary

On February 20, 2025, EPA Region 10 issued an expedited settlement agreement and final order to Sticks & Stones Construction LLC located in Post Falls, Idaho, for violations of TSCA's Lead-Based Paint Renovation, Repair, and Painting (RRP) Rule. EPA Region 10 alleged Sticks & Stones Construction LLC failed to maintain all RRP records for a period of three years after performing renovation on a pre-1978 residential property, as required by the RRP Rule. According to the EJ Screen, the target housing being renovated did occur in an area of potential EJ concern for indexes in the State Percentile. Respondent agreed to pay a penalty amount of $200.

Defendants (1)

  • STICKS & STONES CONSTRUCTION LLCNamed in complaintNamed in settlement

Facilities (1)

  • STICKS & STONES CONSTRUCTION, LLC

    784 SOUTH CLEARWATER LOOP, SUITE B, POST FALLS, ID, 83854

    Registry ID: 110070890683

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • STICKS & STONES CONSTRUCTION LLC (ESA) (TSCA)entered 2025-02-20

    Primary law: TSCA

    Federal penalty: $200

Timeline (4 milestones)

  • 2024-11-25Enforcement Action Data Entered
  • 2025-02-20Complaint Filed/Proposed Order
  • 2025-02-20Final Order Issued
  • 2025-03-03Enforcement Action Closed

Case metadata

EPA activity ID
3604179550
Case number
10-2025-0015
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2025-0015 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.