EPA v. CITY OF CAMBRIDGE POTW - ESA (CWA NPDES)
Final Order With Penalty
Case summary
On August 7, 2024, Region 10 filed an expedited settlement agreement resolving CWA violations at the City of Cambridge Wastewater Treatment Plant located in Cambridge, Idaho. Alleged violations included missing parameters in required reporting and failure to remove sufficient amounts of solids from processed effluent. The Respondent agreed to pay a penalty of $638 and has returned to compliance.
Defendants (1)
- CITY OF CAMBRIDGENamed in complaintNamed in settlement
Facilities (1)
CAMBRIDGE, CITY OF - CAMBRIDGE WWTP
195 EAST CENTRAL, CAMBRIDGE, ID, 83610
Registry ID: 110039696567
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
CITY OF CAMBRIDGE POTW - ESA (CWA NPDES)entered 2024-08-07
Primary law: CWA
Federal penalty: $638
Timeline (5 milestones)
- 2024-05-22Enforcement Action Data Entered
- 2024-08-07Enforcement Action Closed
- 2024-08-07Complaint Filed/Proposed Order
- 2024-08-07NPDES Closed
- 2024-08-07Final Order Issued
Case metadata
- EPA activity ID
- 3603987599
- Case number
- 10-2024-0133
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2024-0133 . Bulk data: ICIS-FEC download summary.