Skip to main content
10-2024-0053Administrative - FormalClosedFY 2024· Region 10

EPA v. LANG STREET FACILITY

Final Order With Penalty

Case summary

On September 9, 2024, Region 10 issued an expedited settlement agreement and final order to Granite Construction Lang Street Facility located in Anchorage, Alaska. Alleged violations included effluent exceedances for total suspended solids on five different occasions. This enforcement action stands to prevent an annual discharge of 8,216 pounds of total suspended solids, 224 pounds of biochemical oxygen demand, 3,350 pounds of chemical oxygen demand, 14 pounds of nitrogen, 28 pounds of total Kjeidahl nitrogen, and 8 pounds of phosphorus into the Campbell Creek. The Respondent agreed to pay a penalty amount of $8,438 and has come back into compliance.

Defendants (1)

  • Granite ConstructionNamed in complaintNamed in settlement

Facilities (1)

  • LANG STREET FACILITY

    10805 LANG STREET, ANCHORAGE, AK, 99515

    Registry ID: 110070388569

Statutes cited

  • CWA 301NPDES Discharge without a Permit

Enforcement conclusions (1)

  • LANG STREET FACILITYentered 2024-09-09

    Primary law: CWA

    Federal penalty: $8,438

Timeline (5 milestones)

  • 2024-03-13Enforcement Action Data Entered
  • 2024-09-09Final Order Issued
  • 2024-09-09Complaint Filed/Proposed Order
  • 2024-10-09NPDES Closed
  • 2024-10-09Enforcement Action Closed

Case metadata

EPA activity ID
3603902529
Case number
10-2024-0053
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
NPDES Discharge without a Permit

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2024-0053 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.