EPA v. NORTHSIDE PLANNED UNIT DEVELOPMENT PHASE 4
Final Order With Penalty
Case summary
On January 17, 2024, EPA Region 10 filed an expedited settlement agreement resolving violations of the Construction General Permit by Northside 4 LLC, located in Vancouver, Washington. Northside 4 LLC is the owner and operator of the Northside Planned Unit Development Phase 4 construction site and failed to ensure stormwater controls are maintained and in operating condition, provide effective controls for concrete washout, and include items in the Stormwater Pollution Prevention Plan as specified by the written standard. Since erosion leads to sediment and other pollutants entering Waters of the United States, EPA estimates that this action has helped reduce 224,621 lbs of sediment from discharging off-site and reaching Lacamas Creek. The Respondent has agreed to pay a penalty of $3,340 and has returned to compliance.
Defendants (1)
- NORTHSIDE 4 LLCNamed in complaintNamed in settlement
Facilities (1)
NORTHSIDE PUD PULTE GROUP
29231 SE 23RD ST, WASHOUGAL, WA, 98671
Registry ID: 110071178820
Statutes cited
- CWA 301/402 — NPDES Permit Violations
Enforcement conclusions (1)
NORTHSIDE PLANNED UNIT DEVELOPMENT PHASE 4entered 2024-01-17
Primary law: CWA
Federal penalty: $3,340
Timeline (5 milestones)
- 2023-10-02Enforcement Action Data Entered
- 2024-01-17NPDES Closed
- 2024-01-17Final Order Issued
- 2024-01-17Enforcement Action Closed
- 2024-01-17Complaint Filed/Proposed Order
Case metadata
- EPA activity ID
- 3603738515
- Case number
- 10-2023-0197
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2023-0197 . Bulk data: ICIS-FEC download summary.