EPA v. FINISH LINE CONSTRUCTION
Final Order With Penalty
Case summary
On October 11, 2023, EPA Region 10 issued an expedited settlement agreement and final order to Finish Line Construction located in Coeur d?Alene, Idaho, for violations of TSCA's Lead-Based Paint Renovation, Repair, and Painting (RRP) Rule. EPA Region 10 alleged Finish Line Construction failed to become RRP firm certified prior to performing renovation work on a pre-1978 residential property, as required by the RRP Rule. According to the EJ Screen, the target housing being renovated occurred in an area of potential EJ concern for indexes in the State Percentile and National Percentile. Respondent agreed to pay a penalty amount of $1,000.
Defendants (1)
- Finish Line ConstructionNamed in complaintNamed in settlement
Facilities (1)
FINISH LINE CONSTRUCTION
3806 NORTH BUCKSKIN ROAD, COEUR D'ALENE, ID, 83815
Registry ID: 110071091401
Statutes cited
- TSCA 402C — Lead: RRP
Enforcement conclusions (1)
FINISH LINE CONSTRUCTIONentered 2023-10-11
Primary law: TSCA
Federal penalty: $1,000
Timeline (4 milestones)
- 2023-08-21Enforcement Action Data Entered
- 2023-10-11Final Order Issued
- 2023-10-11Enforcement Action Closed
- 2023-10-11Complaint Filed/Proposed Order
Case metadata
- EPA activity ID
- 3603690399
- Case number
- 10-2023-0153
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Lead: RRP
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2023-0153 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.