10-2023-0069Administrative - FormalFinal Order IssuedFY 2023· Region 10

EPA v. In the Matter of Ryan Smith and Noah Smith

Final Order No Penalty

Case summary

On April 25, 2023, EPA Region 10 issued an Administrative Order on Consent (AOC) requiring Ryan Smith and Noah Smith to restore impacted wetlands on property in Central, Alaska. Noah Smith is the property owner, and Ryan Smith is the operator conducting the work that impacted over 6 acres of wetlands to prepare the property for a residential cabin development. In addition to being required to restore the wetlands, the AOC requires Ryan Smith and Noah Smith to execute an environmental covenant that will protect the remaining undisturbed wetlands in perpetuity from future development. A CA/FO seeking civil penalties is pending and will be executed at a later date.

Defendants (2)

  • NOAH SMITHNamed in complaintNamed in settlement
  • RYAN SMITHNamed in complaintNamed in settlement

Facilities (1)

  • RYAN SMITH - ALASKA CONSTRUCTION COMPANY

    126.2 STEESE HIGHWAY,, CENTRAL, AK, 99730

    Registry ID: 110071308235

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • In the Matter of Ryan Smith and Noah Smithentered 2023-04-25

    Primary law: CWA

Timeline (3 milestones)

  • 2023-04-06Enforcement Action Data Entered
  • 2023-04-25Complaint Filed/Proposed Order
  • 2023-04-25Final Order Issued

Case metadata

EPA activity ID
3603561130
Case number
10-2023-0069
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2023-0069 . Bulk data: ICIS-FEC download summary.