EPA v. Harbor island, East Waterway AOC T25, Port of Seattle
Case summary
This Settlement provides for the performance of a removal action, including an engineering evaluation and cost analysis (EE/CA), by Respondent and the payment by Respondent of certain response costs incurred by EPA at or in connection with the Terminal 25 South Site (referred to as Terminal 25, T-25 Site, or Site) within the East Waterway Operable Unit (EWOU) of the Harbor Island Superfund Site located in Seattle, Washington.
Defendants (1)
- Port Of SeattleNamed in complaintNamed in settlement
Facilities (1)
HARBOR ISLAND (LEAD)
MOUTH OF DUWAMISH RIVER, SEATTLE, WA, 98134
Registry ID: 110009314401
Statutes cited
- CERCLA 122A — Agreement to Perform Work Under 104B
Enforcement conclusions (1)
Harbor island, East Waterway AOC T25, Port of Seattleentered 2022-03-21
Primary law: CERCLA
Timeline (2 milestones)
- 2022-03-21Final Order Issued
- 2022-04-29Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3603104865
- Case number
- 10-2022-0159
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Agreement to Perform Work Under 104B
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2022-0159 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.