Skip to main content
10-2021-0166Administrative - FormalClosedFY 2021· Region 10

EPA v. Visser Building Co LC

Final Order With Penalty

Case summary

On July 29, 2021, EPA Region 10 issued an expedited settlement agreement and final order to Visser Building Co LC located in Boise, Idaho, for violations of TSCAs Lead-Based Paint Renovation, Repair, and Painting (RRP) Rule occurring in Boise, Idaho. EPA Region 10 alleged that Alcorn Design Build failed to become RRP firm certified prior to performing renovation work on a pre-1978 residential property as required by the RRP Rule. Respondent agreed to pay a penalty amount of $1,000.

Defendants (1)

  • Visser Building Co LCNamed in complaintNamed in settlement

Facilities (1)

  • VISSER BUILDING CO LC

    8312 WEST NORTHVIEW STREET SUITE 120, BOISE, ID, 83704

    Registry ID: 110071072997

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • Visser Building Co LCentered 2021-07-29

    Primary law: TSCA

    Federal penalty: $1,000

Timeline (4 milestones)

  • 2021-07-14Enforcement Action Data Entered
  • 2021-07-29Final Order Issued
  • 2021-07-29Complaint Filed/Proposed Order
  • 2021-08-05Enforcement Action Closed

Case metadata

EPA activity ID
3602765282
Case number
10-2021-0166
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2021-0166 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.