Skip to main content
10-2021-0147Administrative - FormalClosedFY 2021· Region 10

EPA v. Tuma Construction, LLC

Final Order With Penalty

Case summary

On August 5, 2021, EPA Region 10 issued an expedited settlement agreement and final order to Tuma Construction, LLC located in Eagle, Idaho, for violations of TSCAs Lead-Based Paint Renovation, Repair, and Painting (RRP) Rule occurring in Boise, Idaho. EPA Region 10 alleged that Tuma Construction, LLC failed to become RRP firm certified prior to performing renovation work on a pre- 1978 residential property as required by the RRP Rule. Respondent agreed to pay a penalty amount of $200.

Defendants (1)

  • Tuma Construction, LLCNamed in complaintNamed in settlement

Facilities (1)

  • TUMA CONSTRUCTION LLC

    127N FALLING WATER AVENUE, EAGLE, ID, 83616

    Registry ID: 110070923951

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • Tuma Construction, LLCentered 2021-08-05

    Primary law: TSCA

    Federal penalty: $200

Timeline (4 milestones)

  • 2021-07-12Enforcement Action Data Entered
  • 2021-08-05Final Order Issued
  • 2021-08-05Complaint Filed/Proposed Order
  • 2021-08-05Enforcement Action Closed

Case metadata

EPA activity ID
3602763028
Case number
10-2021-0147
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2021-0147 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.