EPA v. IDAHO POWER - BARBER VALLEY DEVELOPMENT INC
Final Order With Penalty
Case summary
EPA Region 10 has issued an Administrative Compliance Order on Consent (?AOC?) to Barber Valley Development, Inc. (?Respondent?) for Clean Water Act (?CWA?) violations in Boise, Idaho, resulting from the discharge of dredged and fill material into wetlands adjacent to Council Spring Creek without a CWA Section 404 permit from the U.S. Army Corps of Engineers. As part of an EPA-approved Restoration and Mitigation Work Plan, Respondent has agreed to remove the unauthorized fill material, restore the site, and improve forested wetland habitat through the creation and enhancement of an offsite mitigation area in Boise. The cost of the compliance action is approximately $113,450. Respondent has also agreed to pay $7,500 in penalties to resolve the CWA violations as part of a Consent Agreement and Final Order.
Defendants (1)
- BARBER VALLEY DEVELOPMENT INCNamed in complaintNamed in settlement
Facilities (1)
IDAHO POWER - BARBER VALLEY DEVELOPMENT INC
EAST WARM SPRINGS AVE, BOISE, ID, 83712
Registry ID: 110070945275
Statutes cited
- CWA 404 — Permits for Dredge and Fill Material
Enforcement conclusions (1)
IDAHO POWER - BARBER VALLEY DEVELOPMENT INCentered 2021-05-27
Primary law: CWA
Federal penalty: $7,500
Timeline (4 milestones)
- 2021-05-05Enforcement Action Data Entered
- 2021-05-27Final Order Issued
- 2021-05-27Complaint Filed/Proposed Order
- 2021-06-22Enforcement Action Closed
Case metadata
- EPA activity ID
- 3602697372
- Case number
- 10-2021-0122
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Permits for Dredge and Fill Material
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2021-0122 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.