EPA v. ASOC for RI/FS at Monsato, P4 Production
Case summary
This Administrative Settlement Agreement and Order on Consent (?Settlement?) is entered into voluntarily by the United States Environmental Protection Agency (EPA), Idaho Department of Environmental Quality (IDEQ), and P4 Production, L.L.C. (Respondent). This Settlement provides for the performance of a supplemental remedial investigation and focused feasibility study (SRI/FFS) by Respondent and the payment of certain response costs incurred by the United States and IDEQ at or in connection with the Monsanto Chemical Co. Superfund Site (the ?Site?) generally located in Soda Springs, Idaho.
Defendants (1)
- P4 ProductionNamed in complaintNamed in settlement
Facilities (2)
RUVEON LLC
1853 HIGHWAY 34, SODA SPRINGS, ID, 83276-0816
Registry ID: 110000743982
RUVEON LLC
1853 HIGHWAY 34, SODA SPRINGS, ID, 83276-0816
Registry ID: 110000743982
Statutes cited
- CERCLA 122A — Agreement to Perform Work Under 104B
Enforcement conclusions (1)
ASOC for RI/FS at Monsato, P4 Productionentered 2021-04-23
Primary law: CERCLA
Timeline (2 milestones)
- 2021-04-23Final Order Issued
- 2021-05-03Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3602695796
- Case number
- 10-2021-0088
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Agreement to Perform Work Under 104B
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2021-0088 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.