Skip to main content
10-2020-0126Administrative - FormalClosedFY 2020· Region 10

EPA v. JC Summers Construction, LLC

Final Order With Penalty

Case summary

On August 14, 2020, Region 10 issued an Expedited Settlement Agreement and Final Order to JC Summers Construction, LLC for a violation of the RRP Rule occurring in Filer, Idaho. The EPA alleged that JC Summers Construction, LLC failed to become RRP firm certified prior to performing renovation work on a pre-1978 residential property as required by the RRP Rule. Respondent agreed to settle and pay a penalty amount of $200.

Defendants (1)

  • JC Summers Construction, LLCNamed in complaintNamed in settlement

Facilities (1)

  • JC SUMMERS CONSTRUCTION, LLC

    3555 NORTH 3400 EAST, KIMBERLY, ID, 83341

    Registry ID: 110070829186

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • JC Summers Construction, LLCentered 2020-08-14

    Primary law: TSCA

    Federal penalty: $200

Timeline (4 milestones)

  • 2020-07-20Enforcement Action Data Entered
  • 2020-08-14Final Order Issued
  • 2020-08-14Enforcement Action Closed
  • 2020-08-14Complaint Filed/Proposed Order

Case metadata

EPA activity ID
3602241367
Case number
10-2020-0126
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2020-0126 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.