Skip to main content
10-2020-0125Administrative - FormalClosedFY 2020· Region 10

EPA v. Quality Exterior Solutions, LLC

Final Order With Penalty

Case summary

On AUGUST 11, 2020, Region 10 issued an Expedited Settlement Agreement and Final Order to Quality Exterior Solutions, LLC for a violation of the RRP Rule occurring in Boise, Idaho. The EPA alleged that Quality Exterior Solutions, LLC failed to become RRP firm certified prior to performing renovation work on a pre-1978 residential property as required by the RRP Rule. Respondent agreed to settle and pay a penalty amount of $1,000.

Defendants (1)

  • Quality Exterior Solutions, LLCNamed in complaintNamed in settlement

Facilities (1)

  • QUALITY EXTERIOR SOLUTIONS, LLC

    1124 SOUTH FIVE MILE ROAD, BOISE, ID, 83709

    Registry ID: 110070829185

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • Quality Exterior Solutions, LLCentered 2020-08-11

    Primary law: TSCA

    Federal penalty: $1,000

Timeline (4 milestones)

  • 2020-07-20Enforcement Action Data Entered
  • 2020-08-11Complaint Filed/Proposed Order
  • 2020-08-11Final Order Issued
  • 2020-08-14Enforcement Action Closed

Case metadata

EPA activity ID
3602241376
Case number
10-2020-0125
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2020-0125 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.