EPA v. J.K. Merrill & Sons, Inc
Final Order With Penalty
Case summary
On June 8, EPA Region 10 ratified a Consent Agreement and Final Order under Section 113 of the Clean Air Act to J.K. Merrill & Sons, Inc., of Pocatello, Idaho resolving violations of 40 C.F.R. Part 63, Subpart ZZZZ at the companys Pocatello, Idaho, sand and gravel plant. The respondent previously entered into a compliance order on consent. The respondent agreed to a civil penalty of $123k.
Defendants (1)
- J.K. Merrill & Sons, IncNamed in complaintNamed in settlement
Facilities (1)
SUNROC COPORATION DBA DEPATCO INC.
1850 TANK FARM ROAD, POCATELLO, ID, 83205
Registry ID: 110046464214
Statutes cited
- CAA 112K — Area Source MACT
Enforcement conclusions (1)
J.K. Merrill & Sons, Incentered 2020-06-08
Primary law: CAA
Federal penalty: $123,000
Timeline (5 milestones)
- 2020-05-04Enforcement Action Data Entered
- 2020-06-08Final Order Issued
- 2020-06-08Complaint Filed/Proposed Order
- 2021-12-01Enforcement Action Closed
- 2021-12-01Air Resolved
Case metadata
- EPA activity ID
- 3602187795
- Case number
- 10-2020-0095
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Area Source MACT
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2020-0095 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.