EPA v. Portland Harbor ASAOC for RD at River Mile 9 West - FMC
Case summary
This settlement provides for the performance of 100% Remedial Design of the River Mile 9 West project area and the payment by Respondent of certain response costs incurred by the EPA, the Oregon Department of Environmental Quality, and the Tribal Governments at or in connection with the work conducted under this settlement, related to the selected remedy for the in-river portion of the Portland Harbor Superfund Site.
Defendants (1)
- FMCNamed in complaintNamed in settlement
Facilities (1)
PORTLAND HARBOR
BETWEEN RM 3.5 & 9.2 IN PORTLAND HARBOR, PORTLAND, OR, 97231
Registry ID: 110009306526
Statutes cited
- CERCLA 122A — Agreement to Perform Work Under 104B
Enforcement conclusions (1)
Portland Harbor ASAOC for RD at River Mile 9 West - FMCentered 2019-12-30
Primary law: CERCLA
Timeline (2 milestones)
- 2019-12-30Final Order Issued
- 2020-01-07Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3602080045
- Case number
- 10-2020-0038
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Agreement to Perform Work Under 104B
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2020-0038 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.