10-2019-0052Administrative - FormalClosedFY 2019· Region 10

EPA v. Pure Design & Build

Final Order With Penalty

Case summary

On May 30, 2019, Region 10 issued an Expedited Settlement Agreement and Final Order to Pure Design & Build located in Boise, Idaho, for violations of the RRP Rule occurring in Boise, Idaho. The EPA alleged that Pure Design & Build failed to become RRP firm certified prior to performing renovation work on pre-1978 residential properties as required by the RRP Rule. Respondent agreed to settle and pay a penalty amount of $1,000.

Defendants (1)

  • Jonathan MundyNamed in complaintNamed in settlement

Facilities (1)

  • PURE DESIGN & BUILD

    48 EAST INDIAN CREEK ROAD, BOISE, ID, 83716

    Registry ID: 110070560437

Statutes cited

  • TSCA 402CLead: RRP

Enforcement conclusions (1)

  • Pure Design & Buildentered 2019-05-30

    Primary law: TSCA

    Federal penalty: $1,000

Timeline (4 milestones)

  • 2019-02-25Enforcement Action Data Entered
  • 2019-05-30Complaint Filed/Proposed Order
  • 2019-05-30Final Order Issued
  • 2019-06-12Enforcement Action Closed

Case metadata

EPA activity ID
3601756602
Case number
10-2019-0052
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lead: RRP