Skip to main content
10-2017-0184Administrative - FormalFinal Order IssuedFY 2017· Region 10

EPA v. Post Road Drum Settlement Agreement

Final Order With Specified Cost Recovery

Case summary

This Settlement Agreement concerns the Post Road Drum Site located in Anchorage, Alaska. EPA alleges that the Site is a facility as defined by Section 101(9) of CERCLA, 42 U.S.C. Section 9601(9). EPA incurred costs under CERCLA in investigating and overseeing clean-up of the site. Pursuant to this Administrative Order On Consent, the two respondents agreed to pay EPA $50,000 to resolve EPA past costs claim. EPA announced this settlement through publication in the Federal Register. No comments were received, and EPA then finalized the AOC.

Defendants (2)

  • SAN LLCNamed in settlement
  • Alaska Railroad CorporationNamed in settlement

Facilities (1)

  • POST ROAD DRUM SITE

    200 N. POST ROAD, ANCHORAGE, AK, 99501

    Registry ID: 110043317461

Statutes cited

  • CERCLA 122HAdministrative Cost Recovery Settlement

Enforcement conclusions (1)

  • Post Road Drum Settlement Agreemententered 2017-12-26

    Primary law: CERCLA

Timeline (2 milestones)

  • 2017-12-26Final Order Issued
  • 2018-10-10Enforcement Action Data Entered

Case metadata

EPA activity ID
3601605676
Case number
10-2017-0184
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Administrative Cost Recovery Settlement

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2017-0184 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.