10-2017-0142Administrative - FormalFinal Order IssuedFY 2017· Region 10

EPA v. CITY OF PLUMMER WWTP, ID - COMPLIANCE ORDER

Final Order No Penalty

Case summary

On September 11, 2017, Region 10 issued a compliance order to address ongoing violations of the Clean Water Act by City of Plummer Wastewater Treatment Plant located in Plummer, Idaho. Respondent, which operates the sewage treatment plant, exceeded its NPDES permit limits for pH, Escherichia coli, biochemical oxygen demand, total suspended solids, total ammonia and total phosphorus. Respondent agreed to pay a penalty of $2,500 and to construct upgrades to the plant, including an equalization project by July 31, 2018. The upgrades will minimize the occurrence of future effluent limit violations.

Defendants (1)

  • City of Plummer, IDNamed in settlement

Facilities (1)

  • PLUMMER, CITY OF - PLUMMER WWTP

    324 TOETLY ROAD (COEUR D'ALENE RESERVATION), PLUMMER, ID, 83851

    Registry ID: 110013719075

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • CITY OF PLUMMER, IDAHO - COMPLIANCE ORDER ON CONSENTentered 2017-09-11

    Primary law: CWA

Timeline (2 milestones)

  • 2017-06-08Enforcement Action Data Entered
  • 2017-09-11Final Order Issued

Case metadata

EPA activity ID
3601068551
Case number
10-2017-0142
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2017-0142 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.