EPA v. Poehls Construction
Final Order With Penalty
Case summary
On April 20, 2017, Region 10 filed an expedited settlement agreement and final order resolving a violation of the Renovation, Repair, and Painting (RRP) Rule under TSCA to Poehls Construction located in North Pole, Alaska. The EPA alleged violations included failing to obtain an initial firm certification from the U.S. Environmental Protection Agency as required by the RRP Rule. Poehls Construction has agreed to pay a penalty amount of $200 to resolve the violation.
Defendants (1)
- Shawn PoehlsNamed in complaintNamed in settlement
Facilities (1)
POEHLS CONSTRUCTION
3356 ELDERBERRY LN, NORTH POLE, AK, 99705
Registry ID: 110069994073
Statutes cited
- TSCA 402C — Lead: RRP
Enforcement conclusions (1)
Poehls Constructionentered 2017-04-20
Primary law: TSCA
Federal penalty: $200
Timeline (4 milestones)
- 2017-01-24Enforcement Action Data Entered
- 2017-04-20Final Order Issued
- 2017-04-20Complaint Filed/Proposed Order
- 2017-04-24Enforcement Action Closed
Case metadata
- EPA activity ID
- 3600914273
- Case number
- 10-2017-0052
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Lead: RRP
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2017-0052 . Bulk data: ICIS-FEC download summary.