EPA v. Gateway Parks LLC
Final Order With Penalty
Case summary
On March 28, 2016, Region 10 filed a consent agreement and final order with Gateway Parks to resolve violations of the National Emission Standards for Hazardous Air Pollutants for asbestos (asbestos NESHAP) resulting from the demolition of multiple buildings in Boise, Idaho. Region 10 alleged that the demolition project started without an asbestos notification to EPA as required by the asbestos NESHAP. The respondent agreed to pay a $10,000 penalty.
Defendants (1)
- Gateway Parks LLCNamed in complaintNamed in settlement
Facilities (1)
GATEWAY PARKS
12000 N HORSESHOE BEND RD, BOISE, ID, 83702
Registry ID: 110064695496
Statutes cited
- CAA 112B — Asbestos
Enforcement conclusions (1)
Gateway Parks LLCentered 2016-03-28
Primary law: CAA
Federal penalty: $10,000
Timeline (4 milestones)
- 2016-02-29Enforcement Action Data Entered
- 2016-03-28Complaint Filed/Proposed Order
- 2016-03-28Final Order Issued
- 2019-02-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 3600656875
- Case number
- 10-2016-0060
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- Asbestos