10-2016-0031Administrative - FormalClosedFY 2016· Region 10

EPA v. TAMARACK MILL LLC, D/B/A/ EVERGREEN FOREST - PENALTY ORDER

Final Order With Penalty

Case summary

On December 14, 2015, Region 10 filed a consent agreement and final order resolving violations of the Clean Water Act by Tamarack Mill, LLC. Respondent, which operates a sawmill, discharged pollutants to waters of the U.S. in violation of EPA's Multi-Sector General Permit for Stormwater Discharges Associated with Industrial Activity (MSGP). Violations include failure to have a complete stormwater pollution prevention plan, failure to submit annual reports, failure to conduct effluent monitoring and failure to have records onsite. The company agreed to pay a penalty of $31,500.

Defendants (1)

  • Tamarack Mill LLCNamed in complaintNamed in settlement

Facilities (1)

  • TAMARACK MILL LLC D/B/A EVERGREEN FOREST

    3555 HIGHWAY 95 SOUTH, NEW MEADOWS, ID, 83654

    Registry ID: 110020061653

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • TAMARACK MILL LLC, D/B/A/ EVERGREEN FOREST - CONSENT AGREEMENT AND FINAL ORDERentered 2015-12-14

    Primary law: CWA

    Federal penalty: $31,500

Timeline (5 milestones)

  • 2015-10-15Enforcement Action Data Entered
  • 2015-12-14Final Order Issued
  • 2015-12-14Complaint Filed/Proposed Order
  • 2016-01-27Enforcement Action Closed
  • 2016-01-27NPDES Closed

Case metadata

EPA activity ID
3600404916
Case number
10-2016-0031
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2016-0031 . Bulk data: ICIS-FEC download summary.