Skip to main content
10-2015-0131JudicialConcludedFY 2015· Region 10

EPA v. Orofino Asbestos Cost Recovery

Final Order With Specified Cost Recovery

Case summary

On August 2, 2016, the U.S. District Court for the District of Idaho entered an ability-to-pay Consent Decree resolving liability and ordering payment of $523,000 in past costs for EPA?s removal actions at the Orofino Asbestos Superfund Site during 2008-2010. The asbestos contamination occurred when Owyhee Construction, a contractor of the Riverside Water and Sewer District, crushed concrete asbestos pipe and then disposed it as fill across several properties in Orofino, Idaho.

Defendants (5)

  • TAYLOR ENGINEERING, INC.
  • OWYHEE CONSTRUCTION, INC.Named in complaintNamed in settlement
  • RIVERSIDE WATER AND SEWER DISTRICTNamed in complaintNamed in settlement
  • JOHN ANDERSON AND RICHARD BURNHAM
  • CLEARWATER OPERATIONS, INC.

Facilities (1)

  • OROFINO ASBESTOS SITE

    GREATER OROFINO AREA, OROFINO, ID, 83544

    Registry ID: 110042266687

Statutes cited

  • CERCLA 107ACost Recovery

Enforcement conclusions (1)

  • Orofino Asbestos Cost Recoveryentered 2016-08-02

    Primary law: CERCLA

Timeline (6 milestones)

  • 2014-12-02Referred To Dept Of Justice
  • 2015-01-20Enforcement Action Data Entered
  • 2015-03-13Complaint Filed With Court
  • 2016-06-13Final Order Lodged
  • 2016-08-02Final Order Entered
  • 2016-08-02Concluded

Case metadata

EPA activity ID
3600054913
Case number
10-2015-0131
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Cost Recovery

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2015-0131 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.