Skip to main content
10-2014-0070JudicialConcludedFY 2014· Region 10

EPA v. POINT RUSTON WDNR SETTLEMENT

Final Order With Specified Cost Recovery

Case summary

Settlement agreement to address WDNR's CERCLA liability at the Commencement Bay, Near Shore-Tide Flats Asarco site. The proposed CD provides for them to perform actions in support of sediment cap work and reimburse EPA for past and future costs related to such work.

Defendants (1)

  • Washington Department of Natural ResourcesNamed in complaintNamed in settlement

Facilities (1)

  • COMMENCEMENT BAY NEARSHORE TIDEFLATS

    ADJ TO RUSTON WAY & TIDEFLATS IND AREA, TACOMA, WA, 98402

    Registry ID: 110009319996

Statutes cited

  • CERCLA 107LLien
  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • POINT RUSTON WDNR SETTLEMENTentered 2014-06-24

    Primary law: CERCLA

Timeline (6 milestones)

  • 2014-03-07Referred To Dept Of Justice
  • 2014-04-03Enforcement Action Data Entered
  • 2014-04-21Final Order Lodged
  • 2014-04-21Complaint Filed With Court
  • 2014-06-24Concluded
  • 2014-06-24Final Order Entered

Case metadata

EPA activity ID
3400225917
Case number
10-2014-0070
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Lien

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2014-0070 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.