10-2014-0005Administrative - FormalClosedFY 2014· Region 10

EPA v. CITY OF GENESEE, IDAHO

Final Order With Penalty

Case summary

The City of Genesee, Idaho operates a wastewater treatment plant which exceeded its NPDES permit limits for biochemical oxygen demand, total suspended solids, pH and E. coli. On December 30, 2013, EPA Region 10 filed a Consent Agreement and Final Order assessing a penalty of $17,700 against the City for these violations of the Clean Water Act.

Defendants (1)

  • City of Genesee, Idaho (SB)Named in complaintNamed in settlement

Facilities (1)

  • GENESEE, CITY OF - GENESEE WWTP

    ONE MILE SW OF CITY CENTER ON MORSCHECK, GENESEE, ID, 83832

    Registry ID: 110039696255

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • CITY OF GENESEE, IDAHO - CONSENT AGREEMENT AND FINAL ORDERentered 2013-12-30

    Primary law: CWA

    Federal penalty: $17,700

Timeline (5 milestones)

  • 2013-10-24Enforcement Action Data Entered
  • 2013-12-30Final Order Issued
  • 2013-12-30Complaint Filed/Proposed Order
  • 2014-01-15NPDES Closed
  • 2014-01-15Enforcement Action Closed

Case metadata

EPA activity ID
3400169070
Case number
10-2014-0005
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations