Skip to main content
10-2012-0151Administrative - FormalClosedFY 2012· Region 10

EPA v. FIR RIDGE HOLSTEINS FARM LLC

Final Order With Penalty

Case summary

On August 30, 2012, Region 10 issued a Consent Agreement and Final Order to Fir Ridge Holsteins under the Clean Water Act to resolve violations of Oregon’s NPDES general permit for concentrated animal feeding operations. Fir Ridge Holsteins agreed to pay a penalty of $7,000.

Defendants (2)

  • Fir Ridge Holsteins Farm LLC (SB)Named in complaintNamed in settlement
  • Scott Ruby

Facilities (1)

  • FIR RIDGE HOLSTEINS LLC

    37400 HIGHWAY 101 SOUTH, CLOVERDALE, OR, 97112

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (1)

  • FIR RIDGE HOLSTEINS FARM LLC - CONSENT AGREEMENT AND FINAL ORDERentered 2012-08-30

    Primary law: CWA

    Federal penalty: $7,000

Timeline (4 milestones)

  • 2012-06-25Enforcement Action Data Entered
  • 2012-08-30Final Order Issued
  • 2012-08-30Complaint Filed/Proposed Order
  • 2012-09-24Enforcement Action Closed

Case metadata

EPA activity ID
3000031931
Case number
10-2012-0151
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2012-0151 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.