EPA v. U.S. DEPARTMENT OF THE INTERIOR, NATIONAL PARK SERVICE - PARADISE WWTP (FF)
Final Order No Penalty
Case summary
For at least the past five years, this facility has been discharging treated domestic wastewater to an unnamed ditch that flows to the Nisqually River, which flows to the Puget Sound without authorization under the CWA. On August 30, 2011, the facility also had a discharge of incompletely treated wastewater in an amount approaching 200,000 gallons. The FFCA requires the facility to submit a permit application, conduct and report monitoring results, and to take measures to prevent reoccurrence of the type of discharge like the one that occurred in August of 2011.
Defendants (1)
- U.S. Dept of the Interior, National Park ServiceNamed in settlement
Facilities (1)
US DOI NPS - PARADISE WWTP
MOUNT RAINIER NATIONAL PARK, PACKWOOD, WA, 98361
Registry ID: 110040464333
Statutes cited
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
USDI, NPS, MOUNT RAINIER NATIONAL PARK PARADISE WWTP - FEDERAL FACILITY COMPLIANCE AGREEMENT (FF)entered 2012-06-08
Primary law: CWA
Timeline (4 milestones)
- 2012-02-27Enforcement Action Data Entered
- 2012-06-08Final Order Issued
- 2017-02-01NPDES Closed
- 2017-02-01Enforcement Action Closed
Case metadata
- EPA activity ID
- 2600103878
- Case number
- 10-2012-0096
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Discharge without a Permit
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2012-0096 . Bulk data: ICIS-FEC download summary.