10-2011-0017Administrative - FormalFinal Order IssuedFY 2011· Region 10

EPA v. JORGENSEN FORGE OUTFALL (LOWER DUWAMISH WATERWAY)

Final Order No Penalty

Case summary

TIME CRITICAL REMOVAL OF TWO LARGE OUTFALL PIPES THAT HAVE BEEN AND CONTINUE TO BE A SOURCE OF PCBS TO THE LOWER DUWAMISH WATERWAY.

Defendants (2)

  • BOEING COMPANYNamed in settlement
  • JORGENSEN FORGE CORPORATIONNamed in settlement

Facilities (1)

  • LOWER DUWAMISH WATERWAY

    RK 2.5 TO RK 10.8, SEATTLE, WA, 98168

    Registry ID: 110009259729

Statutes cited

  • CERCLA 122AAgreement to Perform Work Under 104B
  • CERCLA 107ACost Recovery
  • CERCLA 104E3Entry Access
  • CERCLA 106AImminent & Substantial Endangerment Order

Enforcement conclusions (1)

  • JORGENSEN FORGE OUTFALL (LOWER DUWAMISH WATERWAY)entered 2010-12-01

    Primary law: CERCLA

Timeline (2 milestones)

  • 2010-12-01Final Order Issued
  • 2010-12-03Enforcement Action Data Entered

Case metadata

EPA activity ID
2200032349
Case number
10-2011-0017
Lead agency
EPA
EPA region
10
Voluntary self-disclosure
No
Primary statute
Agreement to Perform Work Under 104B