EPA v. CAV OK LLC - ROCK ISLAND SUBDIVISION
Final Order With Penalty
Case summary
Respondent assessed penalty for failure to obtain coverage under the Construction General Permit (CGP) before conducting ground disturbing activities. Respondent also failed to comply with requirements of the CGP. Limited disturbed areas stabilized. Project is on hold.
Defendants (1)
- CAV OK LLC (SB)Named in complaintNamed in settlement
Facilities (1)
CAV OK LLC
6193 SOUTH MECKEL LANE, COEUR D'ALENE, ID, 83814
Registry ID: 110024819794
Statutes cited
- CWA 301/402 — NPDES Permit Violations
- CWA 301 — NPDES Discharge without a Permit
Enforcement conclusions (1)
CAV OK LLC - EXPEDITED SETTLEMENT AGREEMENTentered 2010-12-27
Primary law: CWA
Federal penalty: $12,250
Timeline (6 milestones)
- 2010-07-12Expedited Settlement Offered
- 2010-10-19Enforcement Action Data Entered
- 2010-12-27Enforcement Action Closed
- 2010-12-27NPDES Closed
- 2010-12-27Complaint Filed/Proposed Order
- 2010-12-27Final Order Issued
Case metadata
- EPA activity ID
- 2200022668
- Case number
- 10-2011-0009
- Lead agency
- EPA
- EPA region
- 10
- Voluntary self-disclosure
- No
- Primary statute
- NPDES Permit Violations
Sourced verbatim from EPA ECHO Enforcement Case Report for case 10-2011-0009 . Bulk data: ICIS-FEC download summary.