Final Order With Specified Cost Recovery
Cost recovery
$3,000,000
Compliance action
$1,600,000
Case summary
LOCKHEED HAS AGREED TO IMPLEMENT THE ROD FOR THE LOCKHEED SHIPYARD OPERABLE UNIT OF THE HARBOR ISLAND SUPERFUND SITE, AND TO PAY ALL EPA/USA PAST AND FUTURE OVERSIGHT COSTS. THERE ARE NO SIGNIFICANT DEVIATIONS FROM THE MODEL RD/RA CONSENT DECREE.
Defendants (1)
- LOCKHEED SHIPYARDNamed in complaintNamed in settlement
Facilities (1)
HARBOR ISLAND (LEAD)
MOUTH OF DUWAMISH RIVER, SEATTLE, WA, 98134
Registry ID: 110009314401
Statutes cited
- CERCLA 122A — Agreement to Perform Work Under 104B
Enforcement conclusions (1)
LOCKHEED SHIPYARD - HARBOR ISLAND SF SITEentered 1995-05-04
Primary law: CERCLA
Timeline (7 milestones)
- 1994-01-01Enforcement Action Data Entered
- 1994-09-30Referred To Dept Of Justice
- 1995-02-27Complaint Filed With Court
- 1995-05-04Final Order Lodged
- 1995-05-04Final Order Entered
- 1995-05-04Concluded
- 2004-03-05Enforcement Action Closed
Case metadata
- EPA activity ID
- 55050
- Case number
- 10-1994-0215
- Lead agency
- EPA
- HQ division
- CER
- Branch
- HAZ2
- EPA region
- 10
- Multimedia
- No
- Voluntary self-disclosure
- No
- Primary statute
- Agreement to Perform Work Under 104B