EPA v. AOC FOR RI/FS AT NORTH INDIAN BEND WASH SITE FOR OU10 (AREA 7) VAPOR INTRUSION
Final Order With Unspecified Cost Recovery
Case summary
This Settlement provides for the performance of a Remedial Investigation and Feasibility Study ( Rl/FS ) by Respondents and the payment by Respondents of certain response costs incurred by the United States, at or in connection with the Area 7 Vapor Intrusion Operable Unit of the North Indian Bend Wash Site (the Site ).
Defendants (1)
- SIEMENS CORPORATIONNamed in settlement
Facilities (1)
INDIAN BEND WASH AREA
MCDOWELL RD & HAYDEN, SCOTTSDALE, AZ, 85253
Registry ID: 110009265892
Statutes cited
- CERCLA 122H — Administrative Cost Recovery Settlement
- CERCLA 107A — Cost Recovery
- CERCLA 104B — CERCLA 104(b)
- CERCLA 122A — Agreement to Perform Work Under 104B
Enforcement conclusions (1)
AOC FOR RI/FS AT NORTH INDIAN BEND WASH SITE FOR OU10 (AREA 7) VAPOR INTRUSIONentered 2026-07-20
Primary law: CERCLA
Timeline (3 milestones)
- 2026-07-20Final Order Issued
- 2026-07-20Enforcement Action Closed
- 2026-07-28Enforcement Action Data Entered
Case metadata
- EPA activity ID
- 3605024727
- Case number
- 09-2026-2502
- Lead agency
- EPA
- EPA region
- 09
- Voluntary self-disclosure
- No
- Primary statute
- Administrative Cost Recovery Settlement
Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2026-2502 . Bulk data: ICIS-FEC download summary.
This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.