Skip to main content
09-2025-2081Administrative - FormalClosedFY 2025· Region 09

EPA v. Peninsula Corridor Joint Powers Board (Caltrain) [AOC]

Final Order No Penalty

Case summary

Caltrain carried out unpermitted work, discharging fill into the Guadalupe River during a bridge replacement project and impacting the habitat of endangered species like steelhead trout and salmon. The Mitigation Project would restore approximately 0.75 acres of degraded instream and riparian habitat.

Defendants (1)

  • Michelle BouchardNamed in complaintNamed in settlement

Facilities (1)

  • CALTRAIN GUADALUPE RIVER BRIDGE

    WILLOW ST AND PEPITONE AVE, SAN JOSE, CA, 95110

    Registry ID: 110071813418

Statutes cited

  • CWA 404Permits for Dredge and Fill Material

Enforcement conclusions (1)

  • Peninsula Corridor Joint Powers Board (Caltrain) [AOC]entered 2025-07-28

    Primary law: CWA

Timeline (3 milestones)

  • 2025-07-28Final Order Issued
  • 2025-07-28Enforcement Action Closed
  • 2025-08-05Enforcement Action Data Entered

Case metadata

EPA activity ID
3604478954
Case number
09-2025-2081
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
Permits for Dredge and Fill Material

Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2025-2081 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.