EPA v. NORTHEAST CHURCH ROCK MINE SITE AND UNITED NUCLEAR CORPORATION MILL SITE PRE-REFERRAL NEGOTIATION
Final Order With Unspecified Cost Recovery
Case summary
The CD is for the reimbursement of costs incurred by the USEPA and the Department of Justice (?DOJ?) for response actions at the Northeast Church Rock Mine Site (?NECR Site?) and the United Nuclear Corporation Site, and performance of work by the by the defendants at the Sites.
Defendants (2)
- UNITED NUCLEAR CORPORATIONNamed in complaintNamed in settlement
- GENERAL ELECTRICNamed in complaintNamed in settlement
Facilities (1)
NORTHEAST CHURCHROCK MINE SITE
NORTH END OF STATE HWY 566, CHURCH ROCK, NM, 87311
Registry ID: 110022266091
Statutes cited
- CERCLA 107A — Cost Recovery
- CERCLA 106A — Imminent & Substantial Endangerment Order
Enforcement conclusions (1)
NORTHEAST CHURCH ROCK MINE SITE AND UNITED NUCLEAR CORPORATION MILL SITE PRE-REFERRAL NEGOTIATIONentered 2026-01-05
Primary law: CERCLA
Timeline (8 milestones)
- 2023-09-14Referred To Dept Of Justice
- 2023-09-14Complaint Filed With Court
- 2023-09-14PRN Sent
- 2023-09-20Enforcement Action Data Entered
- 2025-07-08Final Order Lodged
- 2026-01-05Concluded
- 2026-01-05Enforcement Action Closed
- 2026-01-05Final Order Entered
Case metadata
- EPA activity ID
- 3603720481
- Case number
- 09-2023-2501
- Lead agency
- EPA
- EPA region
- 09
- Voluntary self-disclosure
- No
- Primary statute
- Cost Recovery