09-2022-1514Administrative - FormalFinal Order IssuedFY 2022· Region 09

EPA v. Utulei Sewage Treatment Plant AOC

Case summary

ASPA requested to change the due date of items 29(f) and 29(g), for the Collection System Management Plan (CSMP), System Evaluation and Capacity Assurance Plan (SECAP), and Capital Improvement Plan (CIP) requirements in the Utulei Sewage Treatment Plant and Collection System AOC (Docket No. CWA-309-2022-006) from October 31, 2024 to April 30, 2025. The American Samoa Power Authority agreed to an Administrative Order on Consent with EPA for violations of the Clean Water Act at the Utulei Sewage Treatment Plant and Collection System, including failure to properly operate and maintain its UV disinfection system, resulting in effluent limitation exceedances, failure to prevent sanitary sewer overflows from the collection system, including discharges to Pago Pago Harbor, failure to properly document and report sanitary sewer overflows from the collection system, and failure to conduct and report effluent and receiving water monitoring. The Order requires the American Samoa Power Authority to resume and improve permit requirement monitoring and reporting, create and maintain a spare part inventory for the UV disinfection system, and create and implement a plant to properly manage, operate, and maintain the collection system and improve response to sanitary sewer overflows to minimize water quality impacts.

Defendants (1)

  • Wallon YoungNamed in complaintNamed in settlement

Facilities (1)

  • UTULEI SEWAGE TREATMENT PLANT

    TULUTULU POINT, UTULEI, TUTUILA ISLAND, PAGO PAGO, AS, 96799

    Registry ID: 110039976755

Statutes cited

  • CWA 301/402NPDES Permit Violations

Enforcement conclusions (2)

  • Utulei Sewage Treatment Plant AOCentered 2022-08-02

    Primary law: CWA

  • Utulei Sewage Treatment Plant AOCentered 2025-04-30

    Primary law: CWA

Timeline (3 milestones)

  • 2022-08-02Complaint Filed/Proposed Order
  • 2022-08-19Enforcement Action Data Entered
  • 2025-04-30Final Order Issued

Case metadata

EPA activity ID
3603323566
Case number
09-2022-1514
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
NPDES Permit Violations

Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2022-1514 . Bulk data: ICIS-FEC download summary.