09-2020-3556Administrative - FormalClosedFY 2020· Region 09

EPA v. Calexico Water Treatment Plant

Final Order With Penalty

Case summary

This Expedited Settlement Agreement ( ESA ) is being entered into the United States Environmental Protection Agency ( EPA ), Region IX and City of Calexico ( Respondent ) pursuant to Section 113(a)(3) and (d) of the Clean Air Act (he Act ), 42 U.S.C. Section 7413(a)(3) and (d), and by 40 C.FR. Section 22.13(b). The parties enter into this ESA in order to settle the violations, the Respondent will pay the total penalty amount of $6,420.

Defendants (1)

  • Calexico Water Treatment PlantNamed in complaintNamed in settlement

Facilities (1)

  • CALEXICO WATER TREATMENT PLANT

    545 PIERCE AVE., CALEXICO, CA, 92231

    Registry ID: 110030455692

Statutes cited

  • CAA 112[R][7]Prevention of Accidental Release/Risk Management Plans (RMPs)

Enforcement conclusions (1)

  • Calexico Water Treatment Plantentered 2020-09-25

    Primary law: CAA

    Federal penalty: $6,420

Timeline (4 milestones)

  • 2020-09-25Final Order Issued
  • 2020-09-25Enforcement Action Closed
  • 2020-09-25Complaint Filed/Proposed Order
  • 2020-09-28Enforcement Action Data Entered

Case metadata

EPA activity ID
3602296367
Case number
09-2020-3556
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/Risk Management Plans (RMPs)