09-2019-0035Administrative - FormalClosedFY 2019· Region 09

EPA v. Pittsburg Municipal Marina

Final Order With Penalty

Case summary

This is an Expedited Settlement Agreement between US EPA and the City of Pittsburg, California (Respondent) for Respondent's alleged violation of the Clean Water Act Oil Pollution Prevention Act (SPCC) requirements at the Pittsburg Municipal Marina. To settle the matter, Respondent paid a penalty of $1,950 and certified to EPA that the violation(s) have been corrected.

Defendants (1)

  • City of PittsburgNamed in complaintNamed in settlement

Facilities (1)

  • PITTSBURG MARINA

    51 E MARINA BLVD, PITTSBURG, CA, 94565

    Registry ID: 110070261792

Statutes cited

  • CWA 311JSPCC and/or Federal Response Plan Violations

Enforcement conclusions (1)

  • Pittsburg Municipal Marinaentered 2019-05-23

    Primary law: CWA

    Federal penalty: $1,950

Timeline (4 milestones)

  • 2019-05-23Final Order Issued
  • 2019-05-23Enforcement Action Closed
  • 2019-05-23Complaint Filed/Proposed Order
  • 2019-05-28Enforcement Action Data Entered

Case metadata

EPA activity ID
3601864328
Case number
09-2019-0035
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
SPCC and/or Federal Response Plan Violations