Skip to main content
09-2019-0024Administrative - FormalClosedFY 2019· Region 09

EPA v. E. & J. Gallo Winery

Final Order With Penalty

Case summary

This is a Consent Agreement and Final Order between US EPA and E. & J. Gallo (Respondent) of Modesto, California for Respondent's alleged violations of the Clean Air Act 112(r) Risk Management Plan (RMP) requirements at their winery, located in Fresno, California. Respondent agreed to pay a penalty of $57,839 and must perform a Supplemental Environmental Project, at a cost of no less than $350,000 for emergency shutoff modifications at ammonia refrigeration systems at the facility.

Defendants (1)

  • E. & J. GalloNamed in complaintNamed in settlement

Facilities (1)

  • E & J GALLO WINERY - FRESNO

    5610 EAST OLIVE AVENUE, FRESNO, CA, 93727

    Registry ID: 110071799050

Statutes cited

  • CAA 112[R][1]Prevention of Accidental Release/General Duty Clause

Enforcement conclusions (1)

  • E. & J. Gallo Wineryentered 2019-02-25

    Primary law: CAA

    Federal penalty: $57,839 · SEP: $350,000

Timeline (4 milestones)

  • 2019-02-25Final Order Issued
  • 2019-02-25Enforcement Action Closed
  • 2019-02-25Complaint Filed/Proposed Order
  • 2019-03-04Enforcement Action Data Entered

Case metadata

EPA activity ID
3601765989
Case number
09-2019-0024
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
Prevention of Accidental Release/General Duty Clause

Sourced verbatim from EPA ECHO Enforcement Case Report for case 09-2019-0024 . Bulk data: ICIS-FEC download summary.

This is legal information, not legal advice. Laws vary by jurisdiction and change frequently. Always verify current law with official sources and consult a licensed attorney in your jurisdiction for advice on your specific situation.