09-2014-2508Administrative - FormalFinal Order IssuedFY 2014· Region 09

EPA v. In the Matter for Yosemite Slough Site, San Francisco, CA

Final Order With Specified Cost Recovery

Case summary

The Yosemite Slough Site is an inlet channel tidally connected to central San Francisco Bay. Site sediments are contaminated with lead, PCBs, and other contaminants. EPA has conducted enforcement investigations to identify PRPs and is agreeing to settle with Angelica Gonzalez on an ability to pay basis.

Defendants (1)

  • This settlement is with Angelica GonzalezNamed in complaintNamed in settlement

Facilities (1)

  • YOSEMITE CREEK SEDIMENT

    INTERSECTION OF YOSEMITE AVE AND HAWES S, SAN FRANCISCO, CA, 94124

    Registry ID: 110029528697

Statutes cited

  • CERCLA 122HAdministrative Cost Recovery Settlement

Enforcement conclusions (1)

  • Settlement Agreement In the Matter for Yosemite Slough Site, San Francisco, CAentered 2014-04-02

    Primary law: CERCLA

Timeline (2 milestones)

  • 2014-04-02Final Order Issued
  • 2014-10-10Enforcement Action Data Entered

Case metadata

EPA activity ID
3400299011
Case number
09-2014-2508
Lead agency
EPA
EPA region
09
Voluntary self-disclosure
No
Primary statute
Administrative Cost Recovery Settlement